Current Projects of the Lorain County Engineer

Navigation
Completed Projects | 2008 Projects | Future Projects

Future Projects - 2009 and Beyond

  1. Lear Nagel Road—City of North Ridgeville—State Route 10 to Center Ridge Road: Est. construction cost $5,015,000—80% Fed. 20% Local OPWC.

  2. Cooper Foster Park Rd.—Cities of Lorain and Amherst—State Route 58 to Oberlin Avenue: Est. construction cost $4,020,000—80% Fed. 20% Local OPWC.

  3. State Route 57—Village of Grafton– Railroad north to the corporation limits: Est. construction cost $3,929,000—80% Fed. 20% Local OPWC.

  4. Tower Boulevard widening—City of Lorain– Falbo Avenue to the intersection of Elyria Ave. and E. 36th Street: Est. construction cost $3,500,000—80% Fed. 20% Local OPWC.

  5. Griswold Rd.— Elyria Twp.— Lake Ave. to Leona, widen to 3 lanes: Est. construction cost $2,700,000—80% Fed. 20% Local OPWC.

  6. Oberlin Avenue—City of Lorain—North Ridge Road to 30th Street: Est. construction cost $2,000,000—80% Fed. 20% Local OPWC.

  7. Baumhart Rd.—Kipton, Henrietta, and Brownhelm Township—U.S. Route 20 to Lorain S. Corp: Est. construction cost $1,800,000—80% Fed. 20% Local OPWC.

  8. Cowley Rd.— Eaton Twp.—Crocker Rd. to S.R. 82: Est. construction cost $1,674,000— 80% Fed. 20% Local OPWC.

  9. State Route 301 widening—Village of LaGrange– Taylor St. to north corporation limit: Est. construction cost $1,600,000—80% Fed. 20% Local OPWC.

  10. Abbe Road widening—Sheffield Village– Elyria corporation limits to State Route 254: Est. construction cost $1,600,000—80% Fed. 20% Local OPWC.

  11. Island Rd.— Eaton Twp.—Grafton Township Line to CSX Railroad: Est. construction cost $1,495,000— 80% Fed. 20% Local OPWC.

  12. Butternut Ridge Rd.—Carlisle Township—Oberlin-Elyria Road to Grafton Road: Est. construction cost $800,000—80% Fed. 20% Local OPWC.

  13. Oberlin Road— New Russia and Amherst Township—Oberlin N. Corp to S.R. 113: Est. construction cost $800,000— 80% Fed. 20% Local OPWC.

  14. Grafton Rd.— Carlisle Twp.—S.R. 57 to 16th Street: Est. construction cost $720,000— 80% Fed. 20% Local OPWC.

  15. Oberlin–Elyria Road— New Russia and Carlisle Township– S.R. 511 to Butternut Ridge Road: Est. construction cost $450,000—80% Fed. 20% Local OPWC.

  16. Pyle South Amherst Road—Amherst Township—S. Amherst N. Corp to Amherst S. Corp: Est. construction cost $350,000—80% Fed. 20% Local OPWC.

  17. Lagrange Road—Carlisle Township– U.S. 10 to Oberlin-Elyria Road: Est. construction cost $300,000—80% Fed. 20% Local OPWC.

Future Project Funding: $32,753,000

 



Lorain County Engineer
Ken Carney P.E., P.S.
247 Hadaway St.
Elyria, OH 44035
Elyria: (440) 329-5586
Lorain: (440) 244-6261
Fax: (440) 329-5587
About Us | News Releases | Road Closings
Driving Tips | Projects | Services | Engineering | History
Public Information | Adopt-A-Highway | OPWC
Links | Site Map | Contact Us | Home
LorainCounty.com

Home Contact the Lorain County Engineer Home