- Colorado Ave. — Sheffield Village — City of Lorain to Abbe Rd. Widen to 3 lanes. Estimated construction cost $4,206,000 — 80% Fed. 20% Local OPWC.
- Station Rd. Rehabilitation — Columbia Twp. — Crocker Rd. to Sprague Rd: Estimated construction cost $3,165,000 — 80% Fed. 20% Local OPWC.
- Griswold Rd. — Elyria Twp. — Lake Ave. to Leona, widen to 3 lanes: Estimated construction cost $2,200,000 — 80% Fed. 20% Local OPWC.
- Baumhart Rd. — Kipton, Henrietta, and Brownhelm Township — U.S. Route 20 to Lorain S. Corp: Estimated construction cost $1,800,000 — 80% Fed. 20% Local OPWC.
- Cowley Rd. — Eaton Twp. — Crocker Rd. to S.R. 82: Estimated construction cost $1,673,500 — 80% Fed. 20% Local OPWC.
- Island Rd. — Eaton Twp. — Grafton Township Line to CSX Railroad: Estimated construction cost $1,332,000 — 80% Fed. 20% Local OPWC.
- Russia Rd. — Carlisle and New Russia Twp. — Oberlin — Elyria Rd. To S.R. 58: Estimated construction cost $975,000 — 80% Fed. 20% Local OPWC.
- West Ridge Rd. — Carlisle, Amherst, and Elyria Twp. — Russia Rd. to Dellefield Rd: Estimated construction cost $936,000 — 80% Fed. 20% Local OPWC.
- Butternut Ridge Rd — Carlisle Township — Oberlin — Elyria Road to Grafton Road: Estimated construction cost $800,000 — 80% Fed. 20% Local OPWC.
- Oberlin Road — New Russia and Amherst Township — Oberlin N. Corp to S.R. 113: Estimated construction cost $800,000 — 80% Fed. 20% Local OPWC.
- Grafton Rd. — Carlisle Twp. — S.R. 57 to 16th St: Estimated construction cost $720,000 — 80% Fed. 20% Local OPWC.
- Oberlin — Elyria Road — New Russia and Carlisle Township — S.R. 511 to Butternut Ridge Road: Estimated construction cost $450,000 — 80% Fed. 20% Local OPWC.
- Pyle South Amherst Road — Amherst Township — S. Amherst N. Corp to Amherst S. Corp: Estimated construction cost $350,000 — 80% Fed. 20% Local OPWC.
- Lagrange Road — Carlisle Township — U.S. 10 to Oberlin — Elyria Road: Estimated construction cost $300,000 — 80% Fed. 20% Local OPWC.
Future Project Funding: $19,707,500
|