- Columbia West River Rd./SR 82 Intersection re-align and install traffic signal — Columbia Twp — ODOT administered project. Total cost: $1,012,000 — 80% ODOT, 20% OPWC.
- Oberlin-Elyria Rd. Rehabilitation — Carlisle Twp. — Butternut Ridge Rd. to Elyria Corp Line: Estimated construction cost $900,000 — 80% Fed. 20% Local OPWC.
- Chestnut Ridge Rd. / East River Rd. Rehabilitation — Carlisle and Eaton Twp. — Elyria City Corp Line to North Ridgeville Corp Line: $822,180.55 — 80% Fed. 20% Local — Bid in 2004.
- Capel Rd. Signalization — Eaton Twp. — at proposed Midview Schools driveway: Estimated construction cost $68,600. $34,300 OPWC, $17,150 Local, and $17,150 Midview Schools.
Project Funding for 2005: $2,802,800
|
|
|
|